Tracking the Construction Status

At Pashmina, we are keen on setting high standards in customer experience and transparency. We understand the eagerness and emotions attached with your home. We are passionately hand-crafting your homes and toiling hard to make it ready for you! You can track our periodic construction updates here.

Arrow Up Arrow Down

December 5th, 2018

Construction Status for December 5th, 2018

Block 1:
– External Painting In-Progress
– 10th Floor Internal Plastering
– Windows, Tiling, Electrical & Plumbing : Work In-Progress

Block 2 :
– 14th & Terrace : Slab Work In-Progress
– Internal Plastering In-Progress
– 10th Floor : Internal Block Masonry Work in-progress

Block 3 :
– 9th Floor & 10th Floor : Slab Shuttering in-progress
– 6th Floor : Internal Block Masonry Work in-progress
– Ceiling Plastering Work In-Progress

– Electrical work is in progress at Block 1,2 & 3

November 5th, 2018

Construction Status for November 5th, 2018

Block 1:
– Above Terrace work In-Progress
– OHT Work In-Progress
– External Plastering In-Progress
– Internal Plastering, Windows & Plumbing : Work In-Progress

Block 2 :
– 13th & 14th Floor : Slab Work In-Progress
– Internal Plastering In-Progress
– 10th Floor : Internal Block Masonry Work in-progress

Block 3 :
– 9th Floor : Slab Shuttering in-progress
– 5th Floor : Internal Block Masonry Work in-progress
– Ceiling Plastering Work In-Progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

October 4th, 2018

Construction Status for October 4th, 2018

Block 1:
– Above Terrace work In-Progress
– OHT Work In-Progress
– External Plastering In-Progress
– 1st Floor Internal Plastering : Work In-Progress

Block 2 :
– 13th & 14th Floor : Slab Work In-Progress
– External Plastering In-Progress
– 10th Floor : Internal Block Masonry Work in-progress

Block 3 :
– 8th Floor : Slab Shuttering in-progress
– 4th Floor : Internal Block Masonry Work in-progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

September 4th, 2018

Construction Status for September 4th, 2018

Block 1:
– Above Terrace work In-Progress
– OHT Work In-Progress
– External Plastering In-Progress
– Balcony Railings : Work In-Progress
– 14Th Floor : Internal Block Masonry Work

Block 2 :
– 13th Floor : Slab Shuttering
– External Plastering In-Progress
– 9th Floor : Internal Block Masonry Work in-progress

Block 3 :
– 7th Floor : Slab Shuttering in-progress
– 3nd Floor : Internal Block Masonry Work in-progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

August 4th, 2018

Construction Status for August 4th, 2018

Block 1:
– Terrace Completed
– External Plastering In-Progress
– Terrace Parapet In-Progress
– 14Th Floor : Internal Block Masonry Work

Block 2 :
– 12th Floor : Slab Shuttering
– External Plastering In-Progress
– 8th Floor : Internal Block Masonry Work in-progress

Block 3 :
– 6th Floor : Slab Shuttering in-progress
– 2nd Floor : Internal Block Masonry Work in-progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

July 6th, 2018

Construction Status for July 6th, 2018

Block 1:
– Terrace Slab Shuttering and reinforcement
– Internal Block Masonry Work in-progress

Block 2 :
– 12th Floor : Slab Shuttering
– 11th Floor : Slab work in-progress
– Internal Block Masonry Work in-progress

Block 3 :
– 6th Floor : Slab Shuttering in-progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

June 6th, 2018

Construction Status for June 6th, 2018

Block 1:
– Terrace Slab Shuttering and reinforcement
– Internal Block Masonry Work in-progress

Block 2 :
– 12th Floor : Slab Shuttering
– 11th Floor : Slab work in-progress
– Internal Block Masonry Work in-progress

Block 3 :
– 6th Floor : Slab Shuttering in-progress

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 3

May 04th, 2018

Construction Status for May 07th, 2018

Block 1:
– Slab for the 14th floor
– 14th Floor To Terrace Column work in-Progress

Block 2 :
– Slab for the 11th floor
– 6th Floor : Slab Masonry Work In-Progress

Block 3 :
– Slab in progress for the 6th floor

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1,2 & 2(WC/Bath)

April 06th, 2018

Construction Status for April 06th, 2018

March 06th, 2018

Construction Status for March 06th, 2018

Febuary 02nd, 2018

Construction Status for Febuary 02nd, 2018

Block 1:
– Slab in progress for the 14th floor
– Slab shuttering & reinforcement in progress for the 14th floor

Block 2 :
– Slab in progress for the 11th floor
– Slab concreting in progress for the 11th floor

Block 3 :
– Slab in progress for the 6th floor
– Block 3 Slab shuttering & reinforcement in progress for the 6th floor

– Electrical work is in progress at Block 1,2 & 3
– Waterproofing work is in progress at Block 1& 2(WC/Bath)

January 08th, 2018

Construction Status for January 08th, 2018

Block 1:
– 14th Floor Slab in-Progress
– 14th Floor Slab Shuttering in-Progress
– 10th Floor Block Masonry in-Progress
– 1st Floor Wall Plaster in-Progress

Block 2 :
– 11th Floor Slab in-Progress
– 14th Floor Slab Shuttering in-Progress
– 6th Floor Block Masonry in-Progress
– Ground Floor Wall Plaster in-Progress

Block 3 :
– 6th Floor Slab in-Progress
– 6th Floor Slab Shuttering & Reinforcement in-Progress

December 12th, 2017

Construction Status for December 12th, 2017

  • Block 1 :
    • – 13th Floor Slab in-Progress
    • – 10th Floor Block Masonry in-Progress
    • – 1st Floor Wall Plaster in-Progress
  • Block 2 :
    • – 10th Floor Slab in-Progress
    • – 6th Floor Block Masonry in-Progress
    • – Ground Floor Wall Plaster in-Progress
  • Block 3 :
    • – 5th Floor Slab in-Progress
    • – 2nd Floor Block Masonry in-Progress

October 7th, 2017

Construction Status for October 7th, 2017

  • Block 1 :
    • – 11th Floor Slab @ 133.15lvl
  • Block 2 :
    • – 8th Floor Slab @ 125.50lvl
  • Block 3 :
    • – 3rd Floor Slab @ 111lvl

August 30th, 2017

Construction Status for August 30th, 2017

  • Block 1 :
    • – 10th Floor Slab in-Progress
  • Block 2 :
    • – 7th Floor Slab @ 122.60lvl
  • Block 3 :
    • – 3rd Floor Slab – Shuttering in-Progress
    • – 2nd Floor Slab – Reinforcement in-Progress

August 10th, 2017

Construction Status for August 10th, 2017

  • Block 1 :
    • – 9th Floor Slab in-Progress
    • – Ground Floor Block Masonry Work
    • – First Floor Block Masonry Work
  • Block 2 :
    • – 6th Floor Slab in-Progress
    • – Ground Floor Block Masonry Work
  • Block 3 :
    • – 2nd Floor Slab – Shuttering in-Progress
    • – 1st Floor Slab – Reinforcement in-Progress

July 2017 – Update 2

Construction Status for July 2017

  • Block 1 :
    • – 8th Floor Slab in-Progress
    • – Ground Floor Block Masonry Work
    • – First Floor Block Masonry Work
  • Block 2 : 5th Floor Slab in-Progress
  • Block 3 : 1st Floor Slab in Progress

July 2017 – Update 1

Construction Status for July 2017

  • Block 1 : 7th Floor in-Progress
  • Block 2 : 5th Floor in-Progress
  • Block 3 : 1st Floor in Progress

June 2017

Construction Status for June 2017 – Part 1

May 2017

Construction Status for May

April 2017

  • Pashmina Brookwoods Construction Status for April

  • Pashmina Brookwoods Construction Status for April

  • Pashmina Brookwoods Construction Status for April

  • Pashmina Brookwoods Construction Status for April

  • Pashmina Brookwoods Construction Status for April

  • Pashmina Brookwoods Construction Status for April

Construction Status for April

March 2017

  • Pashmina Brookwoods Construction Status for March PART-3

  • Pashmina Brookwoods Construction Status for March PART-3

  • Pashmina Brookwoods Construction Status for March PART-3

  • Pashmina Brookwoods Construction Status for March PART-3

  • Pashmina Brookwoods Construction Status for March PART-3

  • Pashmina Brookwoods Construction Status for March PART-3

Construction Status for March PART-3

March 2017

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

  • Pashmina Brookwoods Construction Status for March PART-2

Pashmina Brookwoods Construction Status for March PART-2

March 2017

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

  • Pashmina Brookwoods Construction Status for March PART-1

Pashmina Brookwoods Construction Status for March PART-1

March 2017

  • Safety day celebrations in Pashmina Brookwoods

  • Safety day celebrations in Pashmina Brookwoods

Safety day celebrations in Pashmina Brookwoods

February 2017

  • Pashmina brookwoods Block 2 first floor half slab done

Pashmina Brookwoods Construction Status for February PART-3

February 2017

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

  • Pashmina Brookwoods Construction Status for February PART-2

Pashmina Brookwoods Construction Status for February PART-2

February 2017

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

  • Pashmina Brookwoods - BLOCK 1 - SLAB Completed

Pashmina Brookwoods Construction Status for February PART-1

January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

  • Pashmina Brookwoods Construction Status for January 2017

Pashmina Brookwoods Construction Status for January 2017

August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

  • Pashmina Brookwoods Construction Status for August 2015

Pashmina Brookwoods Construction Status for August 2015

July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

  • Pashmina Brookwoods Construction Status for July 2015

Pashmina Brookwoods Construction Status for July 2015

June 2015

  • Pashmina Brookwoods Construction Status for June 2015

  • Pashmina Brookwoods Construction Status for June 2015

  • Pashmina Brookwoods Construction Status for June 2015

  • Pashmina Brookwoods Construction Status for June 2015

  • Pashmina Brookwoods Construction Status for June 2015

Pashmina Brookwoods Construction Status for June 2015